Moving Office: The IT Runbook

An office move fails on connectivity or it fails on phones. Everything else can be recovered on the Monday. The single decision that determines whether your move is calm or catastrophic is when you place the carrier order, and almost every business places it far too late because it is waiting on a lease that is still with the lawyers.

This is the sequence we run. The week markers below are our planning schedule rather than published vendor lead times, and where a carrier or regulator publishes an actual figure we say so explicitly.

Twelve weeks out: three decisions, one of which cannot wait for the lease

Three things get decided at twelve weeks. Two of them are cheap to change later. One is not.

Decision one, and the urgent one: what connects the new site to the internet. Order this before the lease is signed if you possibly can, on a conditional basis, because carrier delivery is the longest single item on the critical path and it does not care about your moving date.

Start by checking what serves the address. nbn Co’s address checker will tell you whether a premises is ready to connect, whether more work is required, or whether it is not currently available, and the technology serving it. That check is free and takes a minute. If the building is served by a non-nbn network such as Opticomm, the process runs through that operator instead. If you need symmetrical, higher-grade connectivity, nbn Enterprise Ethernet is the wholesale product, delivered over dedicated point-to-point fibre wherever nbn has declared the fixed line footprint ready for service, and where fibre is not already in the building it requires a build.

nbn publishes no build or delivery time for Enterprise Ethernet. Its customer-facing pages say only that it will work with your provider to confirm a committed delivery date. The single delivery figure in nbn’s published material is in the wholesale agreement, in the Service Levels Schedule for the Enterprise Ethernet product module, and it is an operational target that nbn states is non-binding, aspirational and not reported to the retail service provider: nbn aims to provide a Committed Delivery Date within 10 business days of the Order Accepted Notification. That is ten business days to be given a date, not ten business days to be connected.

Once the Committed Delivery Date exists it does carry weight, but the weight falls on the wrong side of the counter. If delivery is late against it, nbn pays rebates to your retail service provider, not to you: for an Ordered Product with a Committed Delivery Date on or after 15 November 2021, 100 per cent of the monthly recurring charge whether delivery runs 5 to 9 business days late or 10 business days or more late. That will not fund a fortnight of not trading.

So treat the timeline as entirely retail service provider dependent, which is exactly why it belongs at week twelve rather than week four. Get the Committed Delivery Date in writing from the retail service provider, with the slip terms, and get it before you commit to a moving weekend.

Two things to specify while you are ordering. First, whether you want enhanced service levels. nbn Co lets providers opt in to enhanced service levels on business plans, and defines them across three components: the operational period (the hours during which faults can be worked), the response time, and the rectification time for faults within nbn’s control. A standard consumer-grade service can be restored on a timeline that would be unacceptable for a business that cannot trade without it. Second, order a backup path at the same time. A 4G or 5G failover service, or a satellite link, ordered on day one costs a fraction of what it costs to arrange in a panic in week eleven. If the address is marginal, read business internet options in the outer east and work out which nbn technology serves the address before you assume anything.

Decision two: whether the phone numbers move with you. If you are still on any service with physical dependency on the old address, the numbers have to port, and porting is the second-longest item on the critical path. More on the mechanics below, but the decision is made now.

Decision three: what the new site’s network will be. Platform choice, switch count, access point count, whether the comms room needs a rack or a wall-mounted cabinet. This drives the cabling design, which drives the electrician and the builder, which is why it has to be settled before anyone touches the walls. The comparison is in which network platform the new site should run.

Ten weeks out: survey the new premises properly

The site survey is not a walk-through. It produces a drawing.

Walk the floor plate with the person who will do the cabling and mark: every desk position and how many outlets each needs, every wireless access point position, every printer, every camera, every door with access control, every screen, and the comms room. Note ceiling type and height, because it determines cable pathway and access point mounting. Note where the building’s lead-in and any existing carrier equipment sits, because your comms room wants to be near it.

In the comms room, confirm three things that get missed: dedicated power circuits with enough outlets, ventilation or cooling adequate for a sealed room in a Melbourne February, and physical security. A cabinet in an open corridor that anyone can walk up to is not a comms room. The detail is in designing the comms room and the cabling standards in structured cabling done properly. Work out the UPS you need now, not when the rack is already full.

Two survey items that consistently get skipped. First, meeting rooms: measure them, decide the AV approach, and specify the table power and cable runs before the joiner builds the table. Retrofitting power to a boardroom table is expensive and ugly. Read meeting room AV before you sign off on room design. Second, wireless: do a real predictive design rather than spacing access points evenly, because plasterboard, glass partitioning and metal racking behave very differently.

Finally, agree the labelling scheme now and put it in your documentation set. Every outlet, every patch panel port, every switch port. Do it once at the front and you never do it again.

Eight weeks out: submit the port, and understand what you have submitted

Number porting in Australia runs under the Local Number Portability Code, C540:2023, registered by the ACMA on 1 June 2023. The code introduced completion timeframes where previous versions had none. For a single number being ported, the ACMA states the code generally requires telcos to complete 80 per cent of ports within 8 business days, 90 per cent within 10 business days, and 98 per cent within 15 business days, with the timeframes varying by the number of services and the complexity of the port.

Read that carefully, because most businesses moving office are not porting a single number.

Simple versus complex is the distinction that matters. A simple port (Category A) is a single standalone number. A complex port (Category C) covers multiple lines, DID number ranges, and ISDN services. The percentile timeframes above apply to single-number ports. Complex ports are project managed manually between nominated contacts at the losing and gaining carriers, with a mutually agreed cutover date, and the code does not set a maximum completion timeframe for them. If your business has a main number with a block of direct dial numbers behind it, you have a complex port, and you should treat the timeline as open ended until the carriers agree a date in writing.

Practical points that prevent rejections:

  • The Customer Authority is valid for 90 days from signature. Sign it too early and it expires before the port runs. This is a documented rejection ground.
  • Account details must match exactly. The account number with the losing carrier, the account name, and the service address as the losing carrier holds them. A trading name where the carrier holds a company name will fail.
  • A losing carrier cannot reject a port because you are still in contract. The ACMA’s guidance to telcos is that they must tell a customer about the costs of changing providers, including contract terms, but that is not a basis to block the transfer. Exit fees may still be payable. The port still proceeds.
  • Other valid rejection grounds include the service being disconnected or pending disconnection, a port already pending on that number, the number no longer being with that carrier, and insufficient information supplied.

If you are moving to a cloud phone system anyway, the move is the right moment. Numbers ported to a hosted 3CX system stop being tied to a physical address at all, which removes this problem from every future move. Whoever sells you the voice service takes on obligations under the Telecommunications Consumer Protections Code, C628:2019 as varied in 2022, which is the currently registered version, and the Telecommunications Industry Ombudsman is the external dispute resolution path if it goes wrong. That is covered in what the TCP Code means when your IT provider sells you phones.

Six weeks out: settle the data and server position

Where your data lives determines how hard the weekend is.

If everything is in Microsoft 365 or Google Workspace, and there is no on-premises server, the weekend is easy. People carry laptops to a new building and sign in. Nothing moves. This is the strongest single argument for finishing a cloud migration before a move rather than after it.

If there is an on-premises server, decide now whether it moves or retires. Physically relocating a server is the highest-risk item in the entire move: it has been running for years, it may not survive a power cycle, and its disks do not enjoy being carried down stairs. If it is at end of life, the move is the natural retirement point and the cost of replacing it now is lower than the cost of moving it and replacing it in eighteen months anyway.

Whatever you decide, this is the week you verify that backups you have actually tested restore. Not that they ran. That they restore. Take a full verified backup immediately before anything is unplugged, and keep a copy off site and offline through the entire move.

Also at six weeks: line up the printers. Multifunction devices are usually on a lease with the supplier responsible for relocation, and their calendar is not your calendar. Book the de-install and re-install now, confirm the new IP addressing, and confirm scan-to-email and scan-to-folder settings will be reconfigured, because they always break.

Four weeks out: the sequence that has to hold

By four weeks you should be able to state the following as facts, not hopes:

  • The carrier has a confirmed installation date at the new site, and it is at least two weeks before the move, not the Friday of it.
  • Cabling is scheduled and the comms room will be ready to accept equipment before the movers arrive.
  • The port has a confirmed cutover date and time agreed by both carriers.
  • Every asset that is moving is on an accurate asset register, with a destination location.
  • Building access is arranged for the weekend, including loading dock booking, lift booking and after-hours security access for both buildings.

If the carrier date is not confirmed at four weeks, escalate now and plan a fallback: a temporary 4G or 5G service and a Starlink terminal will keep a business trading for a few weeks, badly but functionally, and arranging that at four weeks is a decision. At four days it is a crisis.

Two weeks out: bring the new site live before you need it

This is the step that separates a calm move from a bad one. Get the new site’s internet, network and wireless working, tested and signed off two weeks before anyone moves into it.

Install the gateway, switches and access points. Bring the carrier service up and test it under load, not with a single speed test. Configure VLANs, wireless, firewall rules and remote access. Put a laptop and a printer on it and use them. Find the problems in a quiet building with two weeks to fix them, rather than at nine o’clock on a Monday morning with 60 people watching.

For a period you will be running both sites simultaneously, which is a small version of the problem in running two sites at once. Keep it deliberately simple: both sites reach the same cloud services independently, and nothing at the new site depends on the old one.

The weekend, hour by hour

Assume a Friday close and a Monday open. The critical instruction: do not port numbers on the Friday of the move.

The reasoning is in the code text, and it is worth quoting because it sets the window you are working inside. C540:2023 defines Standard Hours of Operation as “8 a.m. to 5 p.m. (Standard Time) on Business Days”, where Standard Time means Australian Eastern Standard Time or Australian Eastern Daylight-Saving Time. That is the window. The Code does not oblige a carrier to port outside those hours, and where a carrier does agree to port outside them, that port normally runs through the complex Cat. C process.

Two more numbers from the same code that shape a move. For a complex port, the minimum lead time for a cutover date within Standard Hours of Operation, measured from the gaining provider receiving a valid Complex Port Confirmation Advice, is 5 business days, and losing carriers must support 85 per cent of gaining provider requests for a cutover date within those hours. Rejections on a complex port also have their own clock: the losing carrier must issue a reject advice for 90 per cent of failed validations within three business days and 99 per cent within five business days. Build that into your schedule, because a rejection you learn about on day five costs you a fortnight.

Now apply it. If a Friday port fails or partially completes at four in the afternoon, the window closes at five, the people at both carriers who can fix it have gone home, and you spend the weekend with numbers that ring nowhere and no way to escalate. Port on a Tuesday or a Wednesday, early in the window, with the old service still live and calls forwarding, and keep the whole week either side clear.

The sequence:

Friday, from midday. Last full verified backup. Users log off and shut down. Label and photograph every cable at the back of every device before anything is unplugged, including the server, the rack and the printers. Confirm the old site’s internet stays live over the weekend.

Friday afternoon. Decommission the old comms room. Rack equipment out, patch leads bagged and labelled, switches boxed. Anything not moving goes into a separate, clearly marked pile for disposal, not into the skip.

Friday evening to Saturday morning. Physical transport. The server, if it is moving, travels separately and carefully, not on a pallet with the desks.

Saturday. Rack and cable the new comms room. Patch and test every desk outlet, port by port, against the labelling scheme. This is slow and it is the reason you did the labelling properly. Bring up the server if there is one and verify services before anyone touches a desk.

Saturday afternoon to Sunday. Deploy desk equipment. Every workstation, monitor, dock and phone placed, connected and powered on. Test each desk with a real login, not a link light. Install and test printers, including scan destinations. Test the meeting rooms with a real call on each platform you use.

Sunday. Full walk-through with a checklist. Wireless coverage tested in every corner, including stairwells and the kitchen. Door access and cameras tested. Alarm tested. Sign off, or list what is outstanding and who is fixing it Monday morning.

The first Monday

Have people on site, physically, from before the first staff member arrives. Not on a phone queue. On the floor.

The Monday problems are predictable: a desk that was patched to the wrong port, a printer that will not scan, someone whose docking station did not come, a meeting room that will not connect, and a wireless dead spot behind a filing cabinet nobody surveyed. All small, all fast to fix, all catastrophic to a business’s confidence if the response is a ticket number.

Run a defect list for the whole first week rather than fixing things ad hoc. Everything gets logged, triaged and closed, and at the end of the week you have a record of what the fit-out got wrong, which is worth having when you talk to the builder.

The old site: decommissioning and make-good, which the landlord will invoice you for

This is the part businesses forget until the invoice arrives, and it is genuinely expensive.

Read your make-good clause before the move, not after it. Commercial leases commonly require the premises to be returned to their original condition, and in practice that means removing what you installed. For IT, that typically covers your data cabling, including cable in ceiling and floor spaces, your comms room fit-out including the rack and any cabinets, wall-mounted screens and their brackets, access control hardware on doors, camera mounts, and any penetrations made through walls, floors or ceilings, which have to be patched and made good. Some landlords require the cabling to be removed. Some require it to be left in place. Some require it to be left and certified. These are opposite obligations and only your lease tells you which one applies.

Budget for it and schedule it. Cable removal after the fit-out contractor has left, in an empty building, with a lift booking, is not a job you want to be arranging in the week the keys are due back.

Terminate the services, in the right order. Cancel the old site’s internet service only after the new site has been stable for a period and after any porting has fully completed. Cancel building access, alarm monitoring and any service tied to the old address. Then check the next invoice, because services keep billing long after they stop being used and nobody notices for months.

Deal with the equipment properly. Anything not moving falls into three categories: redeployed, sold or traded, or disposed of. Every device in the last two categories has data on it, including printers and multifunction devices, which hold scanned documents on internal drives, and cameras and access control controllers, which hold footage and personal information. Disposal without a certificate of data destruction is a Privacy Act problem waiting to become a notifiable data breach. The process is in secure device disposal.

Update the documentation. New addresses, new subnets, new device locations, new circuit IDs, new carrier account numbers. If the documentation still describes the old building in six months, the move is not finished.

If you are planning a move and want the carrier order placed before it is too late, that is the one call worth making early. Call TechAssist on 1300 028 324 or get in touch at https://techassist.au/contact/, and we will tell you what the realistic critical path looks like for your specific address and your specific numbers. If you are also fitting out the new space, start with the fit-out checklist for the new premises.